01 Jul 2014
|
Piling Installation Work (Driven Piles) at PT Saipem Indonesia
No: 949498 Date: July 01 2014 Location: Karimun, Kepulauan Riau
|
17 Jun 2014
|
Earthworks at PKMS PT Aditya Agrindo
No: 048/THB-SPB/VI/2014 Date: June 17 2014 Location: Ketapang, West Kalimantan
|
08 Apr 2014
|
Cut and Fill Digester Pond Biogas Plant on PKMS PT Guntung Idamanusa
No: 001/PKS GIN1-BIO/IV/2014 Date: April 08 2014 Location: Indragiri Hilir, Riau
|
02 Apr 2013
|
Drainage, Fencing, Geotextile, Wooden Pile and Base Course at Area Side B Project PKMS PT Sukajadi Sawit Mekar
No: 005/SSM-SMPT.ST-B/PRJ/IV/2013 Date: April 02 2013 Location: Bagendang, Sampit Central Kalimantan
|
21 Jan 2013
|
Land Clearin, Filling, Geotextile and Base Course at Side B Area Project at PT Sukajadi Sawit Mekar
No: 003/SSM-SMPT-ST.B/PRJ/I/2013 Date: January 21 2013 Location: Bagendang, Sampit Central Kalimantan
|
21 Jan 2013
|
Land Clearing and Filling Works at Side B Area at PT Sukajadi Sawit Mekar
No: 001/SSM-SMPT-ST.B/PRJ/2013 Date: January 21 2013 Location: Bagendang, Sampit Central Kalimantan
|
08 Agt 2012
|
Reservoir Works in PKMS PT Kemilau Indah Nusantara
No: 049/THB-SPB/SUB/VIII/12 Date: August 08 2012 Location: Bengalon, Kutim, East Kalimantan
|
01 Jun 2012
|
Earthworks (Cut & Fill) Effluent Pond in PKMS PT Kemilau Indah Nusantara
No: 030/THB-SPB/SUB/V/2012 Date: June 01 2012 Location: Bengalon, Kutim, East Kalimantan
|
20 Mar 2012
|
Earthworks ( Cut and Fill ) Effluent Pond at PMKS PT Kemilau Indah Nusantara
No: 012/THB-SPB/SUB/III/12 Date: March 20 2012 Location: Bengalon Kutim, East Kalimantan
|
20 Mar 2012
|
Cut and Fill Digester Pond Works at PKS PT Sukajadi Sawit Mekar
No: 001/PKS SSM2 - BIO/III/2012 Date: March 20 2012 Location: PKS , PT Sukajadi Sawit Mekar
|
05 Mar 2012
|
Earthworks (Cut & Fill) Effluent Pond in PKMS PT Kaliman Ria Sejahtera
No: 010A/THB-SPB/SUB/III/2012 Date: March 05 2012 Location: Kuala Kurun, Central Kalimantan
|
26 Jan 2012
|
Hauling Road and Infrastructure PT. Gunung Bara Utama
No: GBU-C004/ HR-0112 Date: January 26 2012 Location: Melak, East Kalimantan PT. Gunung Bara Utama (GBU / Company) is intended to construct a houling road to connect the port to coal mine. The length of hauling road is approximately 60 Km which refers to document shown STA 00+000 up to STA 60+000.
The Project Site is situated between Ds Empakuq and S. Hulu Nyahing, in Kutai Barat, East Kalimantan, Indonesia and shown below for information.
|
19 Des 2011
|
Earthworks (Cut & Fill) Mill Area in PKMS PT. Kemilau Indah Nusantara
No : 054/THB-SPB/SUB/XII/2011 Dated : December 19, 2011 Location : Bengalon, Kutim, East Kalimantan
PT Kemilau Indah Nusantara is intended to earthworks (cut & fill) Mill Area in PKMS
|
25 Jul 2011
|
Saipem Karimun Yard Construction Project - Karimun Camp Extension
No. : 626437 Date : July 25, 2011 Location : Karimun, Kepulauan Riau
Saipem Karimun Yard Construction Project - Karimun Camp Extension is intended to supply logistics and procurement work, construction of apartments and studios.
|
07 Jul 2011
|
Cut & Fill Digester Pond Works at PT. Sukajadi Sawit Mekar Project
No. : 001/PKS SSM1-BIO/VII/2011 Date : July 7, 2011 Location : Sebabi, Central Kalimantan
PT Sukajadi Sawit Mekar Project is intended to earthwork for digester pond.
|